Orleans Sewer Construction
Road Construction/Traffic Redirection Information
Main Street Sewer Project
03/28/18 – 04/04/18: Begin running main line on Academy Place from Main St. to Rte 28
03/28/18 – 04/06/18: Begin running main line on 6A from Main St. heading to the Hole in One.
04/05/18 – 04/24/18: Begin running main line on Main St. from the Library heading towards Brewster Cross Rd.
I would anticipate one more library parking lot closure on or about 4/5/18.
04/09/18 – 04/19/18: Begin running main line on 6A from Main St. heading to the 115 Cranberry Highway
04/19/18 – 04/30/18: Run main on Main st. from 6A to Old Colony and then up Old Colony to the Chocolate Sparrow.
04/24/18 – 05/01/18: Run main from Brewster Cross Rd. to Cummings Rd. along Main St.
05/01/18: Begin installing service connections.