Main Street Sewer Project

03/28/18 – 04/04/18:  Begin running main line on Academy Place from Main St. to Rte 28

03/28/18 – 04/06/18:  Begin running main line on 6A from Main St. heading to the Hole in One.

04/05/18 – 04/24/18:  Begin running main line on Main St. from the Library heading towards Brewster Cross Rd.

I would anticipate one more library parking lot closure on or about 4/5/18.

04/09/18 – 04/19/18:  Begin running main line on 6A from Main St. heading to the 115 Cranberry Highway

04/19/18 – 04/30/18:  Run main on Main st. from 6A to Old Colony and then up Old Colony to the Chocolate Sparrow.

04/24/18 – 05/01/18:  Run main from Brewster Cross Rd. to Cummings Rd. along Main St.

05/01/18:  Begin installing service connections.